V Blender – DQ Protocol

Document Number: DQ-OSD-VB-001

Version: 1.0

Date: [Insert Date]

Prepared By: [Insert Name]

Approved By: [Insert Name]

Design Qualification Protocol for V Blender in Solid Dosage Form

Objective: To establish a Design Qualification (DQ) protocol for the V Blender used in the blending of powders and granules, ensuring compliance with regulatory standards and operational requirements.

Scope: This protocol applies to the V Blender utilized in the Production/Blending area for solid dosage forms. It covers the assessment of equipment design, functionality, and suitability for intended use.

Responsibilities:

  • Validation Team: Responsible for executing the DQ protocol and documenting results.
  • Quality Assurance: Responsible for reviewing and approving the DQ protocol.
  • Engineering: Responsible for providing technical support and documentation related to the V Blender.

Prerequisites:

  • Completion of User Requirements Specification (URS) for the V Blender.
  • Installation Qualification (IQ) protocol completed and approved.

Equipment Description:

The V Blender is a cylindrical blending machine designed for the uniform mixing of powders and granules. It operates at variable RPM settings and is equipped with a fill level indicator to ensure proper loading of materials.

Test ID Procedure Acceptance Evidence
DQ-VB-01 Verify RPM settings during operation. RPM within ±10% of specified range. Calibration certificate, operational log.
DQ-VB-02 Check fill level indicator functionality. Indicator accurately reflects fill level. Operational log, visual inspection report.
DQ-VB-03 Measure blending time for specified batch size. Blending time within defined limits. Blending time log, batch records.
See also  Roller Compactor – Deviation Impact Assessment

Detailed Test Cases:

Test Case DQ-VB-01: RPM Verification

Procedure: Set the V Blender to the specified RPM and monitor using a calibrated tachometer.

Expected Result: RPM should remain within ±10% of the specified range.

Test Case DQ-VB-02: Fill Level Indicator Check

Procedure: Load the blender to the specified fill level and verify the indicator’s accuracy.

Expected Result: Fill level indicator should accurately reflect the actual fill level.

Test Case DQ-VB-03: Blending Time Measurement

Procedure: Start blending operation and time the process for the specified batch size.

Expected Result: Blending should be completed within defined time limits as per URS.

Deviations: Any deviations from the acceptance criteria must be documented and reviewed by the Quality Assurance team.

Approvals:

Prepared By: ____________________ Date: ____________

Approved By: ____________________ Date: ____________