Encapsulation Coater (Wurster/Bottom Spray) – DQ Protocol

Document ID: DQ-EC-001

Version: 1.0

Effective Date: [Insert Date]

Reviewed By: [Insert Name]

Approval Date: [Insert Date]

Design Qualification Protocol for Encapsulation Coater (Wurster/Bottom Spray)

Objective: To establish a Design Qualification (DQ) protocol for the Encapsulation Coater used in the coating of microspheres and microcapsules for controlled release applications.

Scope: This protocol applies to the validation of the Encapsulation Coater in the R&D/Production area, focusing on its use for coating particles.

Responsibilities:

  • Validation Team: Ensure compliance with the protocol and documentation.
  • Quality Assurance: Review and approve the DQ protocol.
  • Operations: Execute the procedures outlined in the DQ protocol.

Prerequisites:

  • Completion of User Requirements Specification (URS).
  • Installation Qualification (IQ) of the equipment.
  • Training of personnel on equipment operation.

Equipment Description:

The Encapsulation Coater (Wurster/Bottom Spray) is designed for the coating of particles, facilitating controlled release formulations. Key features include adjustable spray rate, temperature control, and airflow management.

Test ID Procedure Acceptance Criteria Evidence
DQ-EC-001-01 Verify spray rate settings. Spray rate within specified range. Calibration records.
DQ-EC-001-02 Measure temperature during operation. Temperature within defined limits. Temperature logs.
DQ-EC-001-03 Assess airflow uniformity. Airflow meets uniformity specifications. Airflow measurement report.
DQ-EC-001-04 Review audit trail functionality. Audit trail captures all critical actions. Audit trail report.

Detailed Test Cases:

  • Test Case ID: DQ-EC-001-01
    Objective: Verify the spray rate settings of the encapsulation coater.
    Procedure: Set the spray rate and measure output using calibrated equipment.
    Acceptance Criteria: Spray rate must be within the specified range as per URS.
    Expected Outcome: Successful verification of spray rate settings.
  • Test Case ID: DQ-EC-001-02
    Objective: Measure temperature during operation.
    Procedure: Monitor temperature readings throughout the operation.
    Acceptance Criteria: Temperature readings must remain within defined limits.
    Expected Outcome: Successful temperature monitoring.
  • Test Case ID: DQ-EC-001-03
    Objective: Assess airflow uniformity.
    Procedure: Conduct airflow measurements at various points.
    Acceptance Criteria: Airflow must meet uniformity specifications.
    Expected Outcome: Successful assessment of airflow.
  • Test Case ID: DQ-EC-001-04
    Objective: Review audit trail functionality.
    Procedure: Check audit trail logs for completeness and accuracy.
    Acceptance Criteria: Audit trail must capture all critical actions.
    Expected Outcome: Successful review of audit trail.
See also  Microfluidic Mixer (LNP/Liposome Formation) – PQ Protocol

Deviations: Any deviations from this protocol must be documented and approved by the Quality Assurance department.

Approvals:

  • Validation Team Lead: ____________________ Date: __________
  • Quality Assurance: ____________________ Date: __________
  • Operations Manager: ____________________ Date: __________

Data Integrity Checks:

  • Ensure all data logged during testing is backed up and secured.
  • Conduct routine checks to verify data accuracy and completeness.
  • Implement access controls to maintain data integrity.