Grade A/B/C/D Cleanrooms (Facility Qualification) – PQ Protocol

Document Control Number: PQ-2023-001

Version: 1.0

Effective Date: 2023-10-01

Review Date: 2024-10-01

Performance Qualification Protocol for Cleanrooms in Aseptic Processing

Objective: To validate the performance of Grade A/B/C/D cleanrooms to ensure compliance with established standards for aseptic processing.

Scope: This protocol covers the performance qualification of cleanroom facilities used for the aseptic processing of sterile injectables.

Responsibilities:

  • Validation Team: Execute the protocol and document results.
  • Quality Assurance: Review and approve the protocol and results.
  • Engineering: Ensure all equipment and systems are maintained and calibrated.

Prerequisites:

  • Completion of Installation Qualification (IQ).
  • Calibration of all monitoring equipment.
  • Availability of cleanroom environment for testing.

Equipment Description: The facility consists of Grade A, B, C, and D cleanrooms designed for aseptic processing, equipped with HEPA filtration systems, temperature and humidity controls, and airflow visualization systems.

Test ID Procedure Acceptance Criteria Evidence
TP-001 ISO Class Recovery Test ISO Class 5 or better Test report
TP-002 Air Change Rate (ACH) Measurement Minimum 20 ACH Measurement log
TP-003 Differential Pressure (DP) Test Positive pressure maintained DP gauge readings
TP-004 Temperature and Humidity Check Temp: 20-24°C; RH: 30-60% Monitoring logs
TP-005 Airflow Visualization with Smoke No dead spots observed Visualization video

Detailed Test Cases:

  • Test Case TP-001: Conduct ISO Class recovery test using a calibrated particle counter post-operation. Document recovery rates and compare against ISO Class 5 standards.
  • Test Case TP-002: Measure air change rates using an anemometer at various locations. Ensure minimum 20 air changes per hour are achieved.
  • Test Case TP-003: Monitor differential pressure using calibrated gauges. Ensure positive pressure is maintained at all times.
  • Test Case TP-004: Log temperature and humidity using calibrated sensors. Ensure parameters fall within specified limits.
  • Test Case TP-005: Utilize smoke tubes to visualize airflow patterns. Document any dead spots or anomalies.
See also  Planetary Mixer (Wet Mass) – PQ Protocol

Deviations: Any deviations from the acceptance criteria must be documented and investigated. A formal deviation report should be generated for each incident.

Approvals:

  • Validation Team Lead: ____________________ Date: __________
  • Quality Assurance Manager: ____________________ Date: __________
  • Engineering Manager: ____________________ Date: __________