Document Number: OQ-001
Version: 1.0
Effective Date: 2023-10-01
Review Date: 2024-10-01
Prepared By: [Your Name]
Approved By: [Approver’s Name]
Operational Qualification Protocol for Conductivity Meter in QC Laboratory
Objective: To validate the Conductivity Meter used in the QC laboratory for accurate conductivity measurement, ensuring compliance with URS Annex11.
Scope: This protocol applies to the Operational Qualification of the Conductivity Meter utilized in the QC Lab for direct product impact measurements.
Responsibilities:
- Validation Team: Execute the OQ protocol and document results.
- Quality Assurance: Review and approve the OQ protocol and results.
- Laboratory Personnel: Ensure proper operation and maintenance of the Conductivity Meter.
Prerequisites:
- Conductivity Meter must be installed and calibrated.
- All personnel must be trained on the use of the Conductivity Meter.
- Relevant SOPs must be reviewed and available.
Equipment Description:
The Conductivity Meter is an instrument designed for measuring the conductivity of solutions in the QC laboratory. It is critical for ensuring product quality and compliance with specifications.
| Test ID | Procedure | Acceptance | Evidence |
|---|---|---|---|
| OQ-01 | Verify accuracy calibration of the Conductivity Meter. | Calibration within ± 1% of standard. | Calibration report. |
| OQ-02 | Check audit trail functionality. | Complete audit trail for all measurements. | Audit trail report. |
Detailed Test Cases:
Test Case OQ-01: Verify Accuracy Calibration
Objective: To ensure the Conductivity Meter provides accurate measurements.
Procedure: Use standard conductivity solutions to verify calibration.
Acceptance Criteria: Calibration must be within ± 1% of the known standard values.
Evidence: Document results in calibration report.
Test Case OQ-02: Check Audit Trail Functionality
Objective: To confirm that the Conductivity Meter maintains a complete audit trail.
Procedure: Conduct multiple measurements and review the audit trail.
Acceptance Criteria: The audit trail must show all measurement entries with timestamps and user IDs.
Evidence: Document results in audit trail report.
Deviations:
Any deviations from the acceptance criteria must be documented and investigated. A CAPA (Corrective and Preventive Action) process should be initiated as necessary.
Approvals:
Prepared By: ______________________ Date: ___________
Approved By: ______________________ Date: ___________