Chromatography Data System (CDS) – IQ Protocol

Document ID: IQ-CDS-001

Version: 1.0

Date: 2023-10-01

Prepared by: [Your Name]

Approved by: [Approver’s Name]

Installation Qualification Protocol for Chromatography Data System in Quality Control

Objective: To verify that the Chromatography Data System (CDS) is installed correctly and operates as intended to ensure data integrity in the QC Lab.

Scope: This protocol applies to the Installation Qualification of the CDS utilized in the QC Lab for managing chromatography data.

Responsibilities:

  • Validation Team: Responsible for executing the IQ protocol and documenting results.
  • Quality Assurance: Responsible for reviewing and approving the IQ protocol and results.
  • IT Department: Responsible for the installation and configuration of the CDS.

Prerequisites:

  • Completion of user requirements specification (URS).
  • Approval of the validation plan.
  • Installation of necessary hardware and software components.

Equipment Description: The Chromatography Data System (CDS) is a software system designed to manage chromatography data, ensuring compliance with regulatory requirements and maintaining data integrity.

Test ID Procedure Acceptance Criteria Evidence
IQ-01 Verify installation of CDS software. Software is installed without errors. Installation log, screenshots.
IQ-02 Check user access levels and audit trail functionality. Access levels are configured per URS. Audit trail reports, user access logs.
IQ-03 Validate data integrity checks. Data integrity checks pass without discrepancies. Data integrity check reports.
See also  Crystallizer – Traceability Matrix (URS ↔ Tests)

Detailed Test Cases:

Test Case IQ-01: Verify that the CDS software is installed correctly by checking the installation log for errors and confirming that the application launches successfully.

Test Case IQ-02: Assess user access levels by logging in with different user profiles and verifying that permissions align with the URS. Review the audit trail for any unauthorized access attempts.

Test Case IQ-03: Perform data integrity checks by running predefined scenarios that test data input, modification, and deletion, ensuring that the audit trail captures all changes accurately.

Deviations: Any deviations from the acceptance criteria must be documented and addressed through a formal deviation report.

Approvals:

  • Validation Lead: ___________________ Date: ___________
  • Quality Assurance: ___________________ Date: ___________
  • IT Department: ___________________ Date: ___________