Mixing Tank (Non-Jacketed) – IQ Protocol

Document Control Number: IQ-MT-001

Version: 1.0

Effective Date: [Insert Date]

Review Date: [Insert Date]

Installation Qualification Protocol for Mixing Tank in Non-Sterile Liquids Production

Objective: To ensure that the Mixing Tank (Non-Jacketed) is installed correctly and operates according to the defined specifications for mixing non-sterile liquids.

Scope: This protocol applies to the Installation Qualification of the Mixing Tank used in the production of oral liquids, syrups, and suspensions within the manufacturing area.

Responsibilities:

  • Validation Team: Responsible for executing and documenting the IQ protocol.
  • Quality Assurance: Responsible for reviewing and approving the IQ documentation.
  • Production Team: Responsible for providing access to the equipment and necessary operational details.

Prerequisites:

  • Installation of the Mixing Tank must be completed.
  • All necessary utilities (water, electricity) must be connected and functional.
  • Personnel must be trained on the equipment operation.

Equipment Description:
The Mixing Tank is a non-jacketed vessel designed for mixing non-sterile liquids such as oral liquids, syrups, and suspensions. It features adjustable agitation speed and a capacity of [Insert Capacity].

Test ID Procedure Acceptance Evidence
IQ-001 Verify installation according to manufacturer specifications. All components installed as per specifications. Installation checklist.
IQ-002 Check utility connections (water, electricity). Utilities are connected and functional. Utility connection log.
IQ-003 Conduct agitation speed test. Agitation speed within specified range. Agitation speed measurement report.
IQ-004 Measure mixing time for specified liquid. Mixing time meets defined criteria. Mixing time log.
See also  Aseptic Filling (PFS/Vials) for LAI – Qualification Certificate Template

Detailed Test Cases:

  • Test ID: IQ-001
    • Procedure: Review installation documentation and verify against equipment.
    • Acceptance Criteria: All components installed as per specifications.
    • Evidence: Installation checklist signed by the validation team.
  • Test ID: IQ-002
    • Procedure: Inspect and confirm all utility connections are secure and operational.
    • Acceptance Criteria: Utilities are connected and functional.
    • Evidence: Utility connection log reviewed and signed.
  • Test ID: IQ-003
    • Procedure: Set agitation speed and verify with calibrated instrument.
    • Acceptance Criteria: Agitation speed within specified range.
    • Evidence: Agitation speed measurement report.
  • Test ID: IQ-004
    • Procedure: Mix a specified liquid and record the time taken.
    • Acceptance Criteria: Mixing time meets defined criteria.
    • Evidence: Mixing time log documented by the operator.

Deviations: Any deviations from the acceptance criteria must be documented in a deviation report and approved by Quality Assurance.

Approvals:

  • Validation Team Lead: ___________________ Date: ___________
  • Quality Assurance Manager: ______________ Date: ___________
  • Production Supervisor: __________________ Date: ___________