Mixing Tank (Non-Jacketed) – DQ Protocol

Design Qualification Protocol for Mixing Tank Equipment in Non-Sterile Liquids

Document Number: DQ-001

Version: 1.0

Effective Date: [Insert Date]

Prepared By: [Insert Name]

Approved By: [Insert Name]

Objective: To establish a Design Qualification (DQ) protocol for the Mixing Tank used in the production of non-sterile liquids, ensuring it meets specified requirements and is suitable for its intended use.

Scope: This protocol applies to the Mixing Tank (Non-Jacketed) utilized in the production/manufacturing area for the mixing of oral liquids, syrups, and suspensions.

Responsibilities:

  • Validation Team: Prepare and execute the DQ protocol.
  • Quality Assurance: Review and approve the DQ protocol.
  • Production Team: Provide input on operational requirements and assist during testing.

Prerequisites:

  • Completion of User Requirement Specification (URS).
  • Design specifications of the Mixing Tank.
  • Training of personnel on the equipment operation.

Equipment Description: The Mixing Tank is a non-jacketed vessel designed for the efficient mixing of non-sterile liquids. It features adjustable agitation speed and is equipped with a control panel for monitoring mixing time.

Test ID Procedure Acceptance Criteria Evidence
DQ-T01 Verify agitation speed settings. Agitation speed must be within the specified range in the URS. Calibration records and speed test results.
DQ-T02 Measure mixing time during operation. Mixing time must adhere to the limits defined in the URS. Time logs and operational records.

Detailed Test Cases:

  • Test Case 1: Validate agitation speed.
    • Procedure: Set the agitation speed to the maximum and minimum settings. Measure and document the actual speed.
    • Acceptance Criteria: Speed must be within ±10% of the set value.
    • Evidence: Calibration log and measurement data.
  • Test Case 2: Validate mixing time.
    • Procedure: Mix a standard solution and record the time taken to achieve homogeneity.
    • Acceptance Criteria: Mixing time must not exceed specified limits in the URS.
    • Evidence: Time logs and visual inspection results.
See also  Sanitary Transfer Pump (Mag Drive/Centrifugal) – PQ Protocol

Deviations: Any deviations from the acceptance criteria must be documented, and a root cause analysis must be performed to determine the impact on the equipment’s suitability for its intended use.

Approvals:

  • Prepared By: ______________________ Date: ___________
  • Reviewed By: ______________________ Date: ___________
  • Approved By: ______________________ Date: ___________