Mixing Tank (Non-Jacketed) – OQ Protocol

Operational Qualification Protocol for Non-Jacketed Mixing Tank

Document Number: OQ-001

Version: 1.0

Effective Date: 2023-10-01

Prepared By: [Name]

Reviewed By: [Name]

Approved By: [Name]

Objective

The objective of this Operational Qualification (OQ) protocol is to verify that the Mixing Tank (Non-Jacketed) operates according to the defined requirements and meets the specified acceptance criteria for mixing non-sterile liquids.

Scope

This protocol applies to the Mixing Tank (Non-Jacketed) used in the production of non-sterile liquids, including oral liquids, syrups, and suspensions. The testing will confirm that the equipment operates effectively within defined parameters.

Responsibilities

  • Validation Team: Responsible for executing the OQ protocol and documenting results.
  • Quality Assurance: Responsible for reviewing and approving the protocol and results.
  • Production Team: Responsible for providing necessary operational support during testing.

Prerequisites

  • Completion of Installation Qualification (IQ).
  • Training of personnel on the operation of the Mixing Tank.
  • Availability of necessary materials for testing.

Equipment Description

The Mixing Tank (Non-Jacketed) is designed for the mixing of non-sterile liquids. The primary features include:

  • Capacity: [Insert capacity]
  • Agitation mechanism: [Insert type]
  • Control panel: [Insert details]

Test Plan

Test ID Procedure Acceptance Evidence
OQ-001 Verify agitation speed at specified RPM. Within ±5% of target RPM. RPM measurement logs.
OQ-002 Measure mixing time for specified duration. Mixing completed within defined time. Time logs and visual inspection.

Detailed Test Cases

Test Case OQ-001

Objective: Verify agitation speed.

Procedure: Set the Mixing Tank to the target RPM and measure with a calibrated RPM meter.

See also  Drum Lifter – Validation Summary Report (VSR) Template

Acceptance Criteria: The RPM must be within ±5% of the target.

Expected Outcome: RPM readings are within the specified range.

Test Case OQ-002

Objective: Measure mixing time.

Procedure: Start the mixing process and time the duration until the desired consistency is achieved.

Acceptance Criteria: Mixing must be completed within the defined time frame.

Expected Outcome: Mixing completes as per the defined timeline.

Deviations

Any deviations from the acceptance criteria must be documented and assessed for impact on the validation process. A corrective action plan should be developed and approved by the validation team.

Approvals

This protocol requires approvals from the Quality Assurance and Validation teams before execution.