Jacketed Mixing Vessel (SS) – DQ Protocol

Document Number: DQ-001

Version: 1.0

Effective Date: 2023-10-01

Reviewed By: [Name]

Approved By: [Name]

Design Qualification Protocol for Jacketed Mixing Vessel

This protocol outlines the Design Qualification for the Jacketed Mixing Vessel used in the manufacturing of creams, gels, lotions, ensuring compliance with industry standards.

Objective: To validate the design and functionality of the Jacketed Mixing Vessel used for manufacturing semi-solid dosage forms, ensuring it meets specified requirements and operates within defined parameters.

Scope: This protocol applies to the Jacketed Mixing Vessel utilized in the production of creams, gels, lotions, located in the Production/Manufacturing area.

Responsibilities:

  • Validation Team: Overall execution and documentation of the DQ protocol.
  • Quality Assurance: Review and approval of the DQ documentation.
  • Production Team: Operation of the equipment during testing.

Prerequisites:

  • Completion of User Requirements Specification (URS).
  • Installation Qualification (IQ) must be completed prior to DQ execution.
  • Staff training on equipment operation and safety protocols.

Equipment Description:

The Jacketed Mixing Vessel is a stainless steel vessel equipped with temperature control, agitation mechanisms, and PLC logging capabilities. It is designed for the mixing of semi-solid formulations such as creams, gels, and lotions.

Test ID Procedure Acceptance Evidence
DQ-001-01 Verify temperature control functionality. Temperature maintained within ±2°C of set point. Temperature logs from PLC.
DQ-001-02 Check agitation speed settings. Agitation speed within specified range. Agitation speed logs from PLC.
DQ-001-03 Confirm hold time accuracy. Hold time matches the specified duration. PLC logs confirming hold time.
See also  Case Packer – Deviation Impact Assessment

Detailed Test Cases:

  • Test Case DQ-001-01: Conduct a test run to verify that temperature control maintains the specified set point throughout the mixing process. Log temperature readings every 5 minutes.
  • Test Case DQ-001-02: Set the agitation speed to the specified RPM. Verify that the actual speed matches the set speed using the PLC interface.
  • Test Case DQ-001-03: Initiate a mixing cycle and record the time. Validate that the hold time is accurately recorded in the PLC.

Deviations: Any deviations from the acceptance criteria must be documented and assessed for impact on product quality and compliance. A corrective action plan should be developed as necessary.

Approvals:

  • Validation Team Lead: ___________________ Date: __________
  • Quality Assurance Manager: _______________ Date: __________

Data Integrity Checks: Ensure that all PLC logs are backed up and secured, with access limited to authorized personnel. Regular audits of log data should be performed to verify consistency and accuracy.