Differential Pressure Monitoring System – OQ Protocol

Operational Qualification Protocol for Differential Pressure Monitoring System

Document Control:

Document Number: OQ-DPMS-001

Version: 1.0

Effective Date: [Insert Date]

Reviewed By: [Insert Name]

Approved By: [Insert Name]

Objective: To validate the operational performance of the Differential Pressure Monitoring System in monitoring pressure cascades within sterile environments.

Scope: This protocol applies to the Differential Pressure Monitoring System used in the Engineering area for monitoring pressure cascades in sterile injectables/aseptic processes.

Responsibilities:

  • Validation Team: Execute the protocol and document results.
  • Quality Assurance: Review and approve the protocol and results.
  • Engineering: Provide support and necessary documentation for the equipment.

Prerequisites:

  • Completion of Installation Qualification (IQ).
  • Availability of all required documentation and equipment.
  • Training of personnel involved in testing.

Equipment Description:

The Differential Pressure Monitoring System is designed to monitor pressure differentials in sterile environments, ensuring a proper pressure cascade is maintained to prevent contamination. It features alarms for out-of-range conditions and maintains an audit trail of all operations.

Test ID Procedure Acceptance Criteria Evidence
OQ-DP-01 Verify DP range alarms functionality. Alarms activate within specified DP range limits. Alarm logs, screenshots of alarm activation.
OQ-DP-02 Check audit trail functionality. Audit trail logs all changes and events accurately. Audit trail report, system logs.

Detailed Test Cases:

  • Test Case OQ-DP-01: Simulate conditions to trigger DP range alarms. Document alarm response time and accuracy.
  • Test Case OQ-DP-02: Perform operations that modify system settings. Review audit trail for completeness and accuracy.
See also  Depyrogenation Tunnel – Validation Summary Report (VSR) Template

Deviations: Any deviations from the expected results must be documented and assessed for impact on the validation status. A corrective action plan should be implemented as necessary.

Approvals:

  • Validation Team Lead: ___________________ Date: ____________
  • Quality Assurance Manager: _______________ Date: ____________

Data Integrity Checks:

  • Ensure all alarm events are logged with timestamps.
  • Verify that the audit trail cannot be altered post-event.
  • Confirm that data backups are performed regularly and are retrievable.