Objective

The objective of this Performance Qualification (PQ) protocol is to validate the Glass-Lined Reactor (GLR) for use in API manufacturing through chemical synthesis reactions, ensuring compliance with regulatory requirements and operational standards.

Scope

This protocol applies to the Glass-Lined Reactor utilized in the production area for chemical synthesis. It covers all critical parameters impacting product quality and safety.

Responsibilities

  • Validation Team: Overall execution and documentation of the PQ process.
  • Production Team: Operation of the GLR as per validated procedures.
  • Quality Assurance: Review and approval of validation documentation.

Prerequisites

  • Completion of Installation Qualification (IQ) and Operational Qualification (OQ).
  • Availability of qualified personnel for executing the PQ protocol.
  • Approval of User Requirement Specification (URS) and relevant documents.

Equipment Description

The Glass-Lined Reactor (GLR) is designed for chemical synthesis reactions, equipped with temperature, pressure, and agitation controls. It features PLC logging capabilities for data integrity and monitoring.

Test Plan

Test ID Procedure Acceptance Evidence
PQ-01 Verify temperature control accuracy. ±2°C of set point. Temperature logs.
PQ-02 Verify pressure control accuracy. ±5% of set point. Pressure logs.
PQ-03 Verify agitation speed consistency. ±10 RPM of set point. Agitation logs.
PQ-04 Review PLC logs for data integrity. No discrepancies found. PLC log report.
See also  Automated Visual Inspection (AVI) Machine – IQ Protocol

Detailed Test Cases

Test Case: PQ-01

Procedure: Set the GLR to a specified temperature and monitor for stability. Record the temperature at intervals of 5 minutes for 30 minutes.

Acceptance: Temperature must remain within ±2°C of the set point.

Test Case: PQ-02

Procedure: Set the GLR to a specified pressure and monitor for stability. Record the pressure at intervals of 5 minutes for 30 minutes.

Acceptance: Pressure must remain within ±5% of the set point.

Test Case: PQ-03

Procedure: Set the GLR to a specified RPM and monitor for consistency. Record the RPM at intervals of 5 minutes for 30 minutes.

Acceptance: RPM must remain within ±10 RPM of the set point.

Test Case: PQ-04

Procedure: Review PLC logs for any discrepancies during the operation of the GLR.

Acceptance: No discrepancies found in the logs.

Deviations

Any deviations from the acceptance criteria must be documented and investigated. A deviation report should be generated, detailing the nature of the deviation, root cause analysis, and corrective actions taken.

Approvals

Prepared by: ______________________

Title: _____________________________

Date: _____________________________

Reviewed by: ______________________

Title: _____________________________

Date: _____________________________

Approved by: ______________________

Title: _____________________________

Date: _____________________________

Data Integrity Checks