Standard Operating Procedure for Mixing Tank Validation in Non-Sterile Liquids
Purpose: This SOP outlines the validation process for Mixing Tanks used in the production of non-sterile liquids, ensuring compliance with regulatory requirements and product quality.
Scope: This procedure applies to all Mixing Tanks utilized in the manufacturing of oral liquids, syrups, and suspensions within the production area.
Definitions:
- DQ: Design Qualification
- IQ: Installation Qualification
- OQ: Operational Qualification
- PQ: Performance Qualification
- URS: User Requirements Specification
Roles:
- Validation Team: Responsible for executing validation activities and documenting results.
- Quality Assurance: Ensures compliance with SOP and regulatory requirements.
- Production Personnel: Operate the Mixing Tank and provide feedback on performance.
Lifecycle Procedure:
- Conduct Design Qualification (DQ) to confirm the Mixing Tank meets user requirements.
- Perform Installation Qualification (IQ) to verify proper installation and utility connections.
- Execute Operational Qualification (OQ) to ensure the tank operates within defined parameters.
- Complete Performance Qualification (PQ) to validate the Mixing Tank’s performance with actual product.
GDP Controls: Ensure Good Documentation Practices (GDP) are followed throughout the validation process, including accurate record-keeping and data integrity.
Acceptance Criteria Governance: Acceptance criteria shall be derived from the User Requirements Specification (URS) and must be met during each qualification phase.
Calibration/PM Governance: The Mixing Tank shall be calibrated and maintained according to the manufacturer’s specifications and a defined preventive maintenance schedule.
Change Control Triggers: Any modifications to the Mixing Tank, including software updates or hardware changes, shall initiate a change control process.
Revalidation Triggers and Periodic Review: Revalidation is required every 24 months or when significant changes occur that may affect the Mixing Tank’s performance or product quality.
Records/Attachments List:
- Validation Protocols
- Validation Reports
- Calibration Records
- Preventive Maintenance Logs
- Change Control Documentation
- URS Document