Terminal Sterilization Load Carts/Racks – OQ Protocol

Document ID: OQ-001

Version: 1.0

Effective Date: [Insert Date]

Reviewed By: [Insert Name]

Approval Date: [Insert Date]

Operational Qualification Protocol for Terminal Sterilization Load Carts/Racks

Objective: To validate the operational performance of Terminal Sterilization Load Carts/Racks used in the production of IV Infusions.

Scope: This protocol applies to the Operational Qualification of Load Carts/Racks utilized for holding bags and bottles in the autoclave process within the Production area.

Responsibilities:

  • Validation Team: Responsible for executing the qualification protocol.
  • Quality Assurance: Responsible for reviewing and approving the protocol and results.
  • Production Staff: Responsible for the proper use of the equipment during the qualification process.

Prerequisites:

  • Completion of Installation Qualification (IQ).
  • Availability of all necessary equipment and materials.
  • Training of personnel on the use of the load carts/racks.

Equipment Description:

The Terminal Sterilization Load Carts/Racks are designed to hold IV infusion bags and bottles during the autoclave sterilization process. They are constructed from stainless steel to ensure durability and compliance with sterilization requirements.

Test ID Procedure Acceptance Criteria Evidence
OQ-001-01 Verify load configuration stability during sterilization cycles. Load configuration must maintain stability without shifting or collapsing. Photographic evidence and observation logs.
OQ-001-02 Check the integrity of racks under maximum load conditions. Racks must not deform or show signs of failure. Visual inspection reports.

Detailed Test Cases:

  1. Test Case OQ-001-01:
    • Load the cart with bags/bottles as per the defined configuration.
    • Run the sterilization cycle in the autoclave.
    • Document any shifts or collapses during the cycle.
  2. Test Case OQ-001-02:
    • Load the maximum capacity of racks with bags/bottles.
    • Visually inspect the racks before and after the sterilization cycle.
    • Document any deformation or failure.
See also  Hammer Mill – Validation Summary Report (VSR) Template

Deviations: Any deviations from the acceptance criteria must be documented and investigated. A corrective action plan should be developed to address any identified issues.

Approvals:

  • Validation Team Lead: _____________________ Date: ___________
  • Quality Assurance Manager: ________________ Date: ___________