Static Incubator – DQ Protocol

Design Qualification Protocol for Static Incubator

Document Number: DQ-001

Version: 1.0

Effective Date: 2023-10-01

Prepared by: [Your Name]

Approved by: [Approver’s Name]

Objective

The objective of this Design Qualification (DQ) Protocol is to ensure that the Static Incubator used in the Biologics Upstream Processing meets the specified requirements and is suitable for its intended use in cell incubation.

Scope

This protocol applies to the Static Incubator located in the Production/Cell Culture area, focusing on its use for cell incubation in the production of biologics. It covers the validation of critical parameters impacting product quality.

Responsibilities

The Validation Team is responsible for executing this protocol. The Quality Assurance (QA) team will review and approve all documentation. The Equipment Owner is responsible for maintaining the equipment in compliance with this protocol.

Prerequisites

  • Completion of User Requirement Specification (URS) for the Static Incubator.
  • Installation Qualification (IQ) completed and approved.
  • Operational Qualification (OQ) completed and approved.

Equipment Description

The Static Incubator is designed for optimal cell incubation, providing a controlled environment with precise temperature settings. It features PLC logs for monitoring temperature uniformity, ensuring compliance with critical quality parameters.

Test Plan

Test ID Procedure Acceptance Evidence
DQ-01 Verify temperature uniformity using PLC logs. Temperature uniformity within ±2°C of set point. PLC log reports.

Detailed Test Cases

Test Case DQ-01

Objective: To ensure temperature uniformity in the Static Incubator.

Procedure: Review PLC logs to confirm temperature readings at multiple points within the incubator over a specified duration.

See also  Coding Machine (Laser / Inkjet) – DQ Protocol

Acceptance Criteria: All temperature readings must be within ±2°C of the set point.

Evidence: Documented PLC log reports showing temperature readings.

Deviations

Any deviations from the acceptance criteria must be documented and assessed for impact on product quality. A corrective action plan must be developed and executed to address any non-conformances.

Approvals

Prepared by: _____________________ Date: __________

Approved by: _____________________ Date: __________

Data Integrity Checks

Ensure that PLC logs are regularly backed up and that access is restricted to authorized personnel only. Implement checks to confirm the accuracy of logged data against manual temperature readings at regular intervals.